Issue No 09 Southeast Europe · Solar and Storage Intelligence 11 November 2026
Brief No 08 found the peak price below the whole-day average on three exchanges at once and called it the shape of the market. October kept the inversion on all three and almost closed it, while the level rose by between 40 and 56 per cent in a single month. Two months, three exchanges, two different answers to the same question. The discount was never the number worth modelling.

The discount shrank. The level did not.

Three Southeast European exchanges published October 2026 monthly averages for both a whole-day and a peak block. On all three the peak average again cleared below the whole-day average, as it did in September. On all three the gap narrowed sharply.

IBEX in Bulgaria printed a day-ahead baseload average of EUR 232.03/MWh against a peak average of EUR 217.66/MWh for October, on 2.915 TWh traded. SEEPEX in Serbia printed EUR 234.31/MWh baseload against a euro-peak average of EUR 229.17/MWh, on 579 308 MWh. The North Macedonian day-ahead exchange printed an average market-clearing price of EUR 224.74/MWh against a peak-price average of EUR 210.90/MWh, on 186 900 MWh. Each of those figures is reported by Serbia Energy from the exchanges' own October statistics, dated 09.11.2026 for Bulgaria and North Macedonia and 03.11.2026 for Serbia.

The gaps that follow from those published pairs are 6.2 per cent on IBEX, 2.2 per cent on SEEPEX and 6.2 per cent on the Macedonian exchange. Those three percentages are arithmetic on the published averages, not figures any exchange published. In September the same calculation on the figures in Brief No 08 gave 23.3 per cent, 12.1 per cent and 19.3 per cent.

So the direction held and the magnitude collapsed. A revenue model carrying a fixed percentage haircut against baseload would have been wrong in both months, and wrong in opposite directions: far too generous in September, far too harsh in October.

What moved was the level. Bulgaria's baseload average rose about 40 per cent from EUR 166.24/MWh in September. Serbia's rose 56.2 per cent and its euro-peak average rose 73.8 per cent, which is why the gap nearly closed: the peak block rose faster than the day. North Macedonia's average rose 49.3 per cent. Romania, which publishes a weighted average rather than a baseload and peak pair, averaged EUR 239.32/MWh on OPCOM in October on about 1.263 TWh traded, on a report of 09.11.2026 that does not state whether that average is baseload or weighted.

One number published this month shows how far both proxies sit from the thing they stand in for. Reporting ACER's 2026 market integration monitoring on 04.11.2026, Balkan Green Energy News gives the Greek solar capture price for May 2026 as EUR 24.63 against an average market price of EUR 88.95, attributed to DAPEEP. That is a capture price proper, output-weighted against settlement prices, and it is roughly a quarter of the market average for the same month. Neither a baseload average nor a peak block comes close to describing it.

My position. I am inclined to think the useful conclusion from two consecutive months is not a revised discount but the abandonment of the discount as an input. The shape of the day is what changed, and the only inputs that survive a change of shape are the hourly generation profile of the specific plant, hourly settlement prices rather than monthly averages, and whatever is on site that can move energy between hours.

BG
Bulgaria
IBEX day-ahead traded 2.915 TWh in October, about 94 024 MWh a day, with the baseload average at EUR 232.03/MWh and the peak average at EUR 217.66/MWh. The intraday continuous market traded 1.432 TWh at a weighted average of EUR 239.11/MWh. Registered day-ahead participants stood at 155, unchanged from September. Electricity production in the first ten months rose 12.72 per cent year on year to 37.88 TWh, with transmission-connected renewables up 29.37 per cent to 4.51 TWh.
Storage: operating battery power reached 6.23 GW in late October, against 5.41 GW in mid August and 3.43 GW before the end of May, with more than 19 GWh of energy capacity in operating facilities, a figure sourced to ESO via Capital and reported on 03.11.2026. Over 01.10.2026 to 25.10.2026 batteries supplied an average of 18 GWh a day and absorbed an average of 19.9 GWh a day. The counting dispute recorded in Brief No 08 has not been reconciled by anyone, but ESO's own series now runs 3.43 to 5.41 to 6.23 GW on three dates and is internally consistent.
232.03 EUR/MWhn/v GW PV not verified
0.72 GW wind 07.2026
2.71 GW hydro NEK
BESS 6.23 GWOct base · MW AC
RO
Romania
The OPCOM day-ahead market averaged EUR 239.32/MWh in October on about 1.263 TWh traded, for a transaction value of roughly EUR 299.6 million, on a report of 09.11.2026 that does not state whether the average is baseload or weighted. The exchange's own October monthly report could not be opened for this issue, so the basis is carried as unstated rather than assumed. Intraday traded about 147 720 MWh at an average of EUR 232.08/MWh. Eurostat put the rise in Romanian household electricity prices in the first half of 2026 at 51.6 per cent year on year, the largest increase in the European Union; the source does not state the currency basis.
Storage: installed battery power reached 1 162 MW at 01.10.2026, against 494 MW at 01.01.2026, on a report of 05.11.2026 that names no publishing operator or regulator. The Ministry of Energy's EUR 150 million standalone storage call closed on 30.10.2026 at 14:00, against a programme target of at least 2 174 MWh and grant ceilings of EUR 69 000 per MWh and EUR 15 million per undertaking. No ranked list, award or contracted MWh has been published.
239.32 EUR/MWh8.50 GW PV 08.2026
3.30 GW wind 12.2025
6.40 GW hydro 08.2026
BESS 1 162 MWOct DAM, basis unstated · MW AC
GR
Greece
No October monthly average from HEnEx could be verified for this issue. The exchange lists its October 2026 monthly report but the figure is not on the listing page. Reporting of 21.10.2026 gives a current Greek average of EUR 247.82/MWh and says prices topped EUR 400/MWh in some hours, without tying either figure to a named delivery day or to a monthly basis. Neither is used here as a monthly average.
Storage: ADMIE reported on 30.10.2026 that about 800 MW of storage is operating and has helped reduce curtailment, while renewable aggregators are curtailing nearly 75 per cent of surplus generation not sold in the day-ahead market during strong solar periods. Greece connected about 2.7 GW of new wind and solar to the transmission network in the first ten months of 2026, about 2.1 GW of it solar, taking the renewable portfolio to roughly 19 GW. Two large standalone systems were reported online in the window, at Nees Karyes and Thessaloniki, both in the tracker below.
no monthly avg published12 GW PV 10.2026 approx
5.50 GW wind 09.2026
3.40 GW hydro PPC
BESS 800 MWNo Oct monthly avg · MW AC
RS
Serbia
SEEPEX day-ahead traded 579 308 MWh in October, broadly unchanged from September and 13.2 per cent above a year earlier, with an average daily volume of 18 687 MWh. The baseload average rose 56.2 per cent from September to EUR 234.31/MWh and the euro-peak average rose 73.8 per cent to EUR 229.17/MWh. The intraday market traded 3 356.1 MWh at an average of EUR 179.13/MWh. For the delivery day reported as 30.10.2026 SEEPEX recorded a baseload of EUR 303.3/MWh and a peak average of EUR 331.3/MWh, the inversion running the other way on one day inside a month that averaged the first way. The source refers to that day both as Friday and as Thursday, so the day label itself is not firm.
Storage: EMS updated its grid connection request lists on 04.11.2026. A figure of around 2 GW of battery connection agreements in 2026 is in circulation but carries no publishing operator, no as-at date and no MWh, and is not used here as a capacity number. EMS does publish process terms: a simplified study route for an existing active customer with controllable load or storage below 10 MW and no export, at a study fee of EUR 15 000 plus VAT.
234.31 EUR/MWh1.10 GW PV 06.2026
0.58 GW wind 06.2026
2.42 GW hydro EPS
BESS queuedOct base · MW AC
MK
North Macedonia
The organised day-ahead exchange traded 186 900 MWh in October, up 27.6 per cent from 146 498 MWh in October 2025 and 4.3 per cent above September, at an average daily volume of 6 029 MWh. The average market-clearing price was EUR 224.74/MWh, up 49.3 per cent from September, and the peak-price average was EUR 210.90/MWh. The source labels the first figure an average market-clearing price rather than a baseload average, and does not explain why the peak average prints below it, so both are carried as published. MEMO held the country's first guarantees of origin auction, reported on 08.11.2026, placing 34 000 of 35 000 wind units offered at an average of EUR 0.35 each. The report does not give the auction date.
Storage: the Bitola project is structured as a 100 MW / 400 MWh standalone battery at an estimated cost of EUR 98 million, with EBRD, KfW, concessional climate finance and a Western Balkans Investment Framework grant named as sources. The EBRD project record puts its own sovereign-guaranteed loan at up to EUR 33.1 million and shows a board voting date of 02.12.2026, so nothing is committed yet.
224.74 EUR/MWh0.60 GW PV 06.2026
0.04 GW wind 12.2025
0.68 GW hydro ESM
BESS pending boardOct clearing avg · MW AC
ME
Montenegro
No October monthly average was published. BELEN appears in the window only with daily and weekly figures: a weekly average of EUR 295.37/MWh for delivery 2 to 8 November, up 8.2 per cent, with the highest delivery interval at EUR 400.03/MWh. Those are not on the same basis as a monthly average and are not used as one. Montenegro's exports to Italy in the third quarter were reported on 06.11.2026 as around 80 per cent above the same quarter of 2025, on 984 GWh of scheduled exports.
Storage: EPCG and Japan's PowerX signed a memorandum of understanding targeting about 500 MWh over an initial three-year period, described as indicative and not a final investment decision. PowerX dates the signing to 08.05.2026, which is outside this issue's window and is carried here because the regional reporting of 05.11.2026 brought it forward. The Environmental Protection Agency required full environmental impact assessments for two solar projects in the window, the 120 MW Cevo plant on 03.11.2026 and the 60 MW Velestovo plant with battery storage on 05.11.2026, each with two years to submit the study. The Velestovo battery size is not stated in the source.
no monthly avg published0.15 GW PV 06.2026
0.17 GW wind 09.2026
0.68 GW hydro EPCG
BESS MoU onlyNo Oct monthly avg · MW AC
BA
Bosnia and Herzegovina
No exchange published an October monthly average for Bosnia and Herzegovina. Gross electricity production in August was 1 090 GWh against 1 122 GWh a year earlier, with thermal at 598 GWh, net hydropower at 287 GWh and wind and solar at 109 GWh. Those three components sum to 994 GWh against the stated total of 1 090 GWh, and the source does not explain the difference. In the Federation, September gross production was 534 GWh, up 15.3 per cent, split thermal 59.9 per cent, hydropower 31.5 per cent and wind 8.6 per cent. Proposed solar and wind in the connection pipeline tracked by Elektroprijenos BiH total 18.1 GW, 13.5 GW of it solar and 4.6 GW wind, against 5 547 MW of installed generation at the end of 2025, with NOSBiH warning that the grid is not ready for rapid variable growth and flagging 2027 to 2036 for congestion risk.
Storage: no battery project in Bosnia and Herzegovina reached operation, construction, grid connection or an award inside the window. The storage question here is still a queue question. An 18.1 GW pipeline against 5 547 MW installed is the clearest statement in this issue of what happens when connection requests are free and connection capacity is not.
no exchange quote0.21/0.61 GW PV disputed
0.14 GW wind 12.2025
2.10 GW hydro EPBiH
No BESS eventNo day-ahead quote · MW AC
XK
Kosovo
Kosovo now has a published monthly day-ahead price, as a bidding zone on ALPEX. In the exchange's October 2026 monthly report the Kosovo zone traded 118 420.77 MWh at an average clearing price of EUR 239.96/MWh. The B1 unit at Kosovo B is unavailable, raising winter import exposure, on a report of 08.11.2026 that gives the unit at 260 MW without stating whether that is nameplate or available capacity. In the first wind auction Akuo Energy submitted the lowest bid at EUR 75.94/MWh against EUR 78.89/MWh from the Notus Energy and Stublla Energy consortium, with the offer still subject to final evaluation and no award confirmed as at 10.11.2026.
Flexibility procurement: the Ministry of Economy began preparing a second wind auction of up to 200 MW with IFC support on 13.10.2026, while three bids from the first round of up to 100 MW remain under evaluation. Together the two rounds could reach 300 MW, with investment put at EUR 450 million by minister Artane Rizvanolli and up to EUR 500 million by the IFC. Plants would be run by special purpose vehicles with a government share of up to 49 per cent, part-funded through the IMF Resilience and Sustainability Facility.
239.96 EUR/MWh0.03 GW PV 12.2025
0.14 GW wind 12.2025
0.05 GW hydro KEK
No BESS eventOct ALPEX KS zone avg · MW AC
AL
Albania
Albania enters the Brief with this issue. ALPEX, the Albanian power exchange, runs the day-ahead market in two bidding zones, Albania and Kosovo, and reports them in one monthly document. In the October 2026 report the Albania zone traded 128 278.52 MWh at an average clearing price of EUR 240.08/MWh. The report also prints a total day-ahead volume of 186 042.42 MWh and an overall average of EUR 241.02/MWh, a minimum of EUR 1.00/MWh and a maximum of EUR 700.00/MWh at interval level, and a daily range of EUR 97.94/MWh to EUR 366.85/MWh. The printed total does not equal the sum of the two zone volumes it prints alongside, the report does not explain the difference, and it is left unreconciled here. September day-ahead volume was 224.2 GWh, up 75.8 per cent year on year, at EUR 169.72/MWh in the Albania zone on the exchange's September report.
Storage: Matrix Konstruksion and Blessed Investment Group, joint owners of Project Blue at Fier, ordered a 130 MWh Sungrow battery system for the 185 MWp first phase, reported on 07.10.2026, four days before this issue's window opens. A second phase of 164 MWp of PV with an 80 MW / 180 MWh battery is planned. Terms and commissioning dates are not disclosed. The Ministry of Infrastructure and Energy is preparing a 300 MW solar auction with mandatory co-located storage, with EBRD support announced on 05.11.2026 covering grid capacity, auction eligibility, storage regulation, Contract for Difference market readiness and auction documentation. Launch was put at late 2026 or early 2027 in an October ministry statement.
240.08 EUR/MWhn/a GW PV not published
n/a GW wind not published
n/a GW hydro not published
BESS orderedOct ALPEX AL zone avg · MW AC
Basis: Bulgaria and Serbia are monthly day-ahead baseload averages. North Macedonia is the monthly average market-clearing price as its source labels it, not a stated baseload average. Romania is the October day-ahead average as reported on 09.11.2026, on a basis the source does not state; OPCOM's own October monthly report could not be opened for this issue. Kosovo and Albania are the two ALPEX bidding zones, from the exchange's own October 2026 monthly report. Greece and Montenegro published no October monthly average that could be verified for this issue, and their daily or weekly figures are not on the same basis. Bosnia and Herzegovina has no day-ahead quote of its own. Derived figures: the three peak-to-baseload gaps in In Focus are arithmetic on the published averages and are not published by any exchange. The month-on-month percentage changes quoted beside them are published by the sources. Where a figure in this issue is our own sum or ratio it is marked at that point. Capacities: all figures are maximum net generating capacity, that is AC. Figures show the month in which they were verified, or an operator label where the source is a standing operator disclosure rather than a dated publication. Figures tagged 12.2025 or earlier were sourced for Brief No 07 and are carried with their original date rather than restated as current. Bulgarian solar is shown as not verified. Two in-window reports give about 7.2 GW and about 7.3 GW, neither attributed to ESO or to the ministry and neither with a stated as-at date, so no figure is printed rather than printing one that cannot be traced. Greek solar at about 12 GW and the 19 GW renewable total carry no explicit as-at date in the source, and the 2.7 GW of additions is specifically transmission-connected capacity. Albania is new to the table and no installed-capacity figure by technology with a named publisher and an as-at date could be verified for it this month, so those cells read not published rather than carrying an estimate. Bosnia and Herzegovina solar remains disputed between 212 MW at IRENA and 608 MW at Bankwatch for the same date, with 305.59 MW in larger plants per the regulator DERK.
Mkt Project MW MWh Status Note
BGTotal operating BESS power 6 230>19 000 Operating Late October, sourced to ESO via Capital and reported on 03.11.2026, against 5 410 MW in mid August and 3 430 MW before the end of May. Over 01.10.2026 to 25.10.2026 batteries supplied an average of 18 GWh a day and absorbed an average of 19.9 GWh a day. The energy capacity figure carries no as-at date beyond late October.
BGTenevo BESS-2, Yambol 246512.5 Financed EBRD announced a EUR 30 million senior loan on 02.11.2026 inside a EUR 60 million package with Raiffeisen Bank International, to Tenevo Solar Technologies, a 50:50 joint venture involving Renalfa IPP. It is co-located with the existing 242 MWp PV plant and the 65 MW / 260 MWh BESS-1. Brief No 08 printed 311 MW / 773 MWh for the site across three battery phases. The EBRD describes two systems whose components sum to 311 MW and 772.5 MWh, and finances the larger one on 02.11.2026, a month after the inauguration.
ROTotal installed BESS power 1 162n/a Operating At 01.10.2026, against 494 MW at 01.01.2026, on a report of 05.11.2026 that names no publishing operator or regulator. No MWh figure accompanies it. Treat the MW series as indicative until Transelectrica or ANRE publishes it.
ROScornicesti standalone, Olt 127254 Completing R.Power with Eiffel Investment Group and EPC contractor Parapet, on a EUR 46 million package secured in June that includes EUR 44 million of EBRD investment and bridge financing plus a EUR 2.3 million BGK guarantee securing an optimisation contract with GEN-I. The named components sum to EUR 46.3 million against the stated EUR 46 million package, and the source does not explain the difference. Reported on 13.10.2026 as expected online early next year.
RODumbrava-Deal, Neamt 50100 Under construction Parapet and MetaWealth were reported on 12.10.2026 to have started construction, with civil works under way and full commissioning targeted for spring 2027. The source gives no start date and no investment figure.
ROMedgidia, Constanta n/a612 Share purchase signed ENNA Solar was reported on 26.10.2026 to have signed for 100 per cent of CIC Grenn Energy Medgidia, the company name spelled as in the source, holder of 166 MWp of planned solar plus the battery, on about 204 hectares, expected generation 265 932 MWh a year, construction from the first quarter of 2027 and operation from the first quarter of 2028. Price undisclosed, closing subject to foreign investment screening and competition clearance.
GRNees Karyes, Larissa 330790 Inaugurated Metlen and Karatzis Group inaugurated the country's largest standalone battery, reported on 16.10.2026, on a EUR 170 million investment, in a joint venture held 51 per cent by Karatzis and 49 per cent by Metlen, built in six months.
GRThessaloniki industrial site 100200 Completed HELLENiQ Renewables completed the park at the group's industrial facilities, reported on 12.10.2026, on an investment of about EUR 50 million. Reporting of the same date names Huawei as supplier; the company itself does not.
GRTotal operating standalone BESS ~800n/a Operating ADMIE on 30.10.2026, with no MWh figure published alongside it. Brief No 08 recorded about 400 MW of the 900 MW awarded in the three standalone auctions as connected at 29.09.2026; the 800 MW figure is for all operating standalone storage and is not the same measure.
MKBitola, ESM 100400 Pending board Estimated cost EUR 98 million, with EBRD, KfW, concessional climate finance and a Western Balkans Investment Framework grant named as sources on 05.11.2026. The EBRD project record puts its own sovereign-guaranteed loan at up to EUR 33.1 million and shows a board voting date of 02.12.2026. Lender-by-lender amounts are not published.
ALProject Blue, Fier n/a130 Ordered Matrix Konstruksion and Blessed Investment Group ordered a Sungrow system for the 185 MWp first phase, reported on 07.10.2026, four days before this issue's window opens. The order covers 26 PowerTitan 2.0 battery units and 13 MVS3460-LS units. A second phase of 164 MWp of PV with an 80 MW / 180 MWh battery is planned. Terms and commissioning dates not disclosed, and the first phase battery is given in MWh only.
MEEPCG with PowerX n/a~500 Memorandum Targeted over an initial three-year period, described in the 05.11.2026 regional report as indicative and not a final investment decision. PowerX dates the signing to 08.05.2026, outside this issue's window.
RSConnection process terms n/an/a Process EMS updated its connection request lists on 04.11.2026. Published terms: a simplified study route for an existing active customer with controllable load or storage below 10 MW and no export capability, at a study fee of EUR 15 000 plus VAT. The circulating figure of around 2 GW of battery connection agreements in 2026 has no publishing operator, no as-at date and no MWh, and is not carried here as capacity.
BAConnection queue, solar and wind 18 100n/a Queue 13 500 MW of solar and 4 600 MW of wind applications tracked by Elektroprijenos BiH, against 5 547 MW of installed generation at the end of 2025, for which the source gives no publishing institution. NOSBiH warns the grid is not ready for rapid variable growth and flags 2027 to 2036 for congestion and system-operation risk. No battery project reached any milestone in the window.
XKWind auctions, rounds one and two up to 300n/a Bids in Preparation of a second round of up to 200 MW with IFC support began 13.10.2026, while three bids from the first round of up to 100 MW remain under evaluation. Akuo Energy submitted the lowest first-round bid at EUR 75.94/MWh against EUR 78.89/MWh from the Notus Energy and Stublla Energy consortium, with no award confirmed as at 10.11.2026. This is wind, not storage, and is tracked here because it is the flexibility-adjacent procurement in that market this month.
EUR 800M
RO
Nuclearelectrica approves an EIB loan for the Cernavoda Unit 1 refurbishment. The extraordinary general shareholders' meeting approved taking the loan, reported on 29.10.2026, at a 22-year maturity with a four-year grace period on principal. Brief No 08 reported both Cernavoda units shut and about 1.4 GW of normally stable output removed from the Romanian system. This is the financing of the fix, on a timetable measured in decades rather than in alert periods.
EUR 60M
BG
EBRD and Raiffeisen finance the second Tenevo battery. Announced on 02.11.2026, with EUR 30 million from the EBRD and EUR 30 million in parallel financing from Raiffeisen Bank International, to Tenevo Solar Technologies, for 246 MW / 512.5 MWh co-located with the existing 242 MWp PV plant and the 65 MW / 260 MWh first battery. The sequence is worth noting: the complex was inaugurated at the start of October with both batteries counted, and the second one was financed a month later.
EUR 78M
RO
OMV Petrom and Renovatio start commercial operations at three solar parks. Tandarei, Bucovat and Cazanesti total 130 MW and were reported operational in a company filing of 28.10.2026, with OMV Petrom's net attributable share around 65 MW. The filing gives no commercial operation date. Total investment EUR 78 million, including a EUR 26 million grant from the national recovery plan, and estimated gross annual production of 0.2 TWh.
BAM 160.1M
BA
Local consortium wins the 60 MW Hrgud wind farm against a Chinese bidder. Elektroprivreda Republike Srpske selected a consortium of El Promet, Lager, Ventum Gradnja, GP Gradip, Eko-Euro Tim, Vendom, Gradjevinski institut and Nasa Banka at BAM 160.1 million, about EUR 81.9 million on the source's own conversion, reported on 06.11.2026. The source gives no selection date and dates the tender launch to 20 July without a year. In a market with an 18.1 GW connection queue and no battery milestones, the deals that close are still thermal-adjacent and wind.
560 MWp
GR
Masdar buys the Enipeas solar plant from Lightsource bp. The acquisition was reported on 26.10.2026 at an undisclosed price. The plant sits in Larissa and neighbouring Phthiotis and was built by Ameresco Sunel Energy. It is expected to be operational by the end of 2026, and closing is expected by then subject to regulatory approval. No source gives the date of agreement. The same page gives the size both as more than 550 MW and as 560 MW in peak capacity. Masdar states an intention to add battery storage without naming a capacity, and signed a memorandum with Khazna Data Centers.
EUR 32.3M
BA
Bistrica hydro opens a grid tender as its cost estimate rises. The Republic of Srpska project with China's AVIC was reported on 02.11.2026 to have opened an EPC plus financing tender for the Miljevina substation and the lines connecting the B1, B2a and B3 plants. Bids are due 14 December and completion is set within two years of building permits. The source gives no opening date. The estimated project cost has moved from about EUR 103 million to more than EUR 171 million.
EUR 25.6M
BA
Republika Srpska guarantees further borrowing for its power utility. Reported on 09.11.2026: the entity guaranteed about EUR 25.6 million for Elektroprivreda Republike Srpske and EUR 9.2 million for RiTE Ugljevik, about EUR 34.8 million between them on our own addition, with about EUR 2.5 million more arranged through factoring, taking group financing activity in 2026 above EUR 100 million. The source gives no date for the guarantee decision. Read it alongside the Hrgud award: the same balance sheet is funding both the wind build and the lignite plant.
Greece

Electricity market legislation reported on 03.11.2026 as submitted to parliament would charge data centres an annual levy of EUR 15 000 per MW, payable to local communities, and require a grid connection guarantee of EUR 200 000 per MW. At least 60 per cent of annual consumption would have to come from renewable generation, and connection applications above 200 MW would get priority assessment. The ministry had presented the connection rules on 12.10.2026 with the same guarantee figure at a three year duration. Reporting disagrees on the submission date, 31.10.2026 in one account and 03.11.2026 in another, so neither is stated as fact here. No act number is published and the bill is subject to parliamentary approval. For anyone sizing storage in Greece this is the first time a price has been put on the load side of the flexibility question rather than the generation side.

Bulgaria

Parliament passed amendments to the Renewable Energy Sources Act at second reading on 06.11.2026, completing transposition of Directive (EU) 2023/2413, whose deadline was 21 May 2025. The amendments extend the validity of grid connection opinions for wind generators and are presented as encouraging decentralised generation and storage. The bill was submitted by the Council of Ministers on 10.07.2026. No State Gazette number has been published, so the operative text and its entry into force are not yet citable.

Bosnia and Herzegovina

The Republic of Srpska government was reported on 29.10.2026 to be tightening the rules for solar development on farmland, after 3 064 hectares of agricultural land were reclassified between 2022 and 2024, 588 hectares in 2022, 1 141 in 2023 and 1 335 in 2024, with more than 60 per cent of that area attributed to solar projects. Municipalities currently permit solar installations up to 150 kW. The measure is a response to land conversion, not to grid capacity, and the 18.1 GW queue is untouched by it.

Romania

The EUR 150 million standalone storage call closed on 30.10.2026 at 14:00 without a published outcome. The published terms are grant ceilings of EUR 69 000 per MWh and EUR 15 million per undertaking, against a programme target of at least 2 174 MWh. Submission figures circulating before the deadline could not be verified for this issue and are not carried. No ranked list, award amount or contracted MWh has been published, and no Romanian act, order or emergency ordinance dated inside this window was located.

Serbia and Montenegro

No new or amended act was located in either market inside the window, and no official gazette reference was found. That is the result of searching, not an assumption. Both markets were active in permitting and in procurement during the month, which is recorded in the sections above, but neither produced a published legislative change in this window.

One clarification first, on our own text. Brief No 08 printed the Tenevo complex at 311 MW / 773 MWh of storage across three battery phases, brought into commercial operation at the inauguration at the start of October. The EBRD announcement of 02.11.2026 describes the site differently: an existing 242 MWp PV plant with one 65 MW / 260 MWh battery, plus a second battery of 246 MW / 512.5 MWh that it is now financing. Two systems, not three phases. The power adds to the same 311 MW and the energy to 772.5 MWh against the 773 MWh we printed. What was not visible last month is that the larger of the two reached financial close only in November. I do not think the earlier line was wrong on the information then available. I do think it shows how quickly an inauguration and a financing can be read as one event when they are a month apart.

On the discount, I would now stop using it. Two months, three exchanges, and two answers that differ by between three and five and a half times. September gave 23.3, 19.3 and 12.1 per cent below the whole-day average. October gives 6.2, 6.2 and 2.2 per cent, on my own arithmetic from the published pairs, so the gap narrowed by a factor of 3.8 in Bulgaria, 3.1 in North Macedonia and 5.5 in Serbia. A fixed haircut would have overstated revenue in one month and understated it in the next. The published Greek capture price of EUR 24.63 for May 2026 against a market average of EUR 88.95 says the same thing from the other direction: where the real number is published, it sits nowhere near either block average. The haircut was always a convenience. It is now a measurably wrong one.

What I would take forward is the direction of the Bulgarian series, not a ratio. ESO's own figures run 3.43 GW before the end of May, 5.41 GW in mid August and 6.23 GW in late October. Two in-window reports put Bulgarian solar at about 7.2 and about 7.3 GW, neither attributed and neither dated, so I am not going to build a parity argument on a denominator I cannot source. The battery series alone says enough: a system that added roughly 2.8 GW of battery power in five months is being rebuilt around the shape of the day, and the question for an operating park stops being what the annual average price will be and becomes which hours it can still sell into and what it owns that can move energy out of the others.

And the queues keep answering the same way. Bosnia and Herzegovina carries 18.1 GW of solar and wind applications against 5 547 MW installed, with its own system operator saying the grid is not ready. Kosovo has a lowest wind bid of EUR 75.94/MWh on the table, not yet awarded, in a system that has lost a thermal unit for the winter. Albania is preparing 300 MW of solar with mandatory co-located storage while its grid capacity is still being assessed. Three markets, three stages, one constraint. An existing connection with something on it that can shift hours is still the asset worth owning in this region, and nothing in October changed that.